Project Log

January
23 - Project Problem Discussed
28 - Meeting with Dr. Kroos to discuss design ideas
February
4 - Meeting with Dr. Kroos to discuss design report specifications due on 2/9/04
6 - Type design report specifications
9 - Group research and brainstorming for design elements
11-Brainstorming session
18- Group meeting
25 - Meeting with Dr. Kroos to discuss abstract and design
March
8 - Meeting with Mr. Morrow and Mr. Divalerio to discuss design project and use of St. Marys Pool
10 - Meeting with Dr. Kroos to discuss the use of LabView and thermocouples in the design
17 - Finishing up report for the EPA P3 Design Competition
19 - Meeting with Dr. Kroos to discuss P3 Design Competition and revise the written report
24 - Compiled P3 Award Application
31 - Group meeting to discuss the final proposal
April
14 - Meeting with Dr. Kroos to discuss the oral presentation
21 - Group compiled oral presentation
26 - Oral Presentation
July
15 - Recieved email from Dr. Kroos about the EPA proposal status
September
2 - Meeting with Dr. Kroos to discuss the new semester and our direction

15 - Began solid works drawings and acquired blueprints to St. Mary's pool

16 - Meeting with Dr. Kross to discuss budgeting options

23- Meeting with Dr. Kroos to discuss instumentation and funding letters

30- Meeting with Dr. Kroos to alternative construction if we can not get and AC unit

October
2 - Meeting with Dr. Kroos to discuss the new semester and our direction

15 - Began solid works drawings and acquired blueprints to St. Mary's pool

16 - Meeting with Dr. Kross to discuss budgeting options

23- Meeting with Dr. Kroos to discuss instumentation and funding letters

30- Meeting with Dr. Kroos to alternative construction if we can not get and AC unit

 

 

This Week
  1. Meeting with Dr. Kroos
  2. Group Meeting
  3. Equipment research

 

Next Week
  1. Meeting with Dr. Kroos
  2. Group Meeting
  3. Equipment research

 page contains a list of scheduled


events, and key milestones and


Home | Design Team Members | Design Schedule | Archive | Search | Pictures | Contact Information

 Copyright C.H.I.P.S. 2005.
For problems or questions regarding this web contact [ryan.reed@villanova.edu].
Last updated: 04/24/05.